Project Timeline:

  • Steel structure – mid October 2024
  • Concrete floor slabs – December 2024
  • Roof – December 2024
  • Interior Framing – January 2025
  • Interior Mechanical, electrical and plumbing – January 2025
  • Building enclosure – February 2025
  • Drywall & Painting – May 2025
  • Parking lot and paving – June 2025
  • Outdoor Plaza – July 2025
  • Fixtures & Finishes – August 2025
  • Estimated completion & move in – September 2025